Workshop on R-Mode in 2019

Printer-friendly versionPDF version
Parent: 
ENG Radionavigation Services
Step No.: 
3.2.4
Category: 
task
Status: 
in progress
Priority: 
normal
Duration unit: 
Day
Price Mode: 
Not Applicable
Currency: 
Euro
Billing status: 
Not billable

ENG Committee – 2018-22 Work Programme

TASK 

3.2.4     Workshop on R-Mode in 2019

Objectives of the task

Bring experts of different IALA committees and other together and identify most promising concepts for the R-Mode implementation while discussing available proposals.

Expected outcome

  • Technical specification of R-Mode system and service
  • Technical Requirements for R-Mode implementation on MF, AIS and VDES Strategy for deployment
  • Review and update of the roadmap

Strategic Alignment

Goal: G2

Strategy: S1, S3

Scope (Describe key items that are in scope/out of scope)

  •  Consolidation of the user requirements on R-Mode system
  • Implementation aspects of R-Mode on VHF (VDES/AIS)
  • Implementation aspects of R-Mode on MF
  • Results from simulations and test field trails

Expected Sessions for Completion:

Session number:

 

 

+

 

+

 

 

 

 

 

 

 

 

1                 2                    3                 4                    5                    6                       7

 

Brief and concise description of the work to be undertaken and programme milestones where appropriate.

Key milestones / Remaining key milestones for completing the task include:

  • Identify most important topics for the workshop
  • Define workshop target group of external experts and IALA members
  • Review of ongoing R-Mode activities
  • Ask and invite experts to prepare elaborated proposals for the discussions on the workshop
  • On the workshop: Discuss about most suitable approaches for the R-Mode implementation
  • On the workshop: Identify further key issues (unsolved issues) to solve in the next future
  • On the workshop: Develop a roadmap (technology and standardisation) for the implementation of R-Mode as alternative PNT System
  • The workshop is being considered as an opportunity to form agreements on the way forward and it is clear that work to develop ideas and proposals is needed to ensure the topics are suitably mature to enable decisions to be made
  • Prepare input to IALA committees

Task Revision

Ver.

Date

Part / Section Revised

Requirement for Revision

1

2018.10.18

ENG8

 

 

 

 

 

Date: 
Thursday, October 18, 2018 - 12:15 to Thursday, September 5, 2019 - 12:15